Project Description:
WESTFORD- INTERSECTION & SIGNAL IMPROVEMENTS @ ROUTE 110 & TADMUCK ROAD
The project involves roadway widening, signalization, turning lanes, sidewalks, crosswalks, retaining walls, stormwater management improvements and culvert replacement.
Location:
  • Town of Westford
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Arvind Patel
    Construction Bid Price: $2,383,284.50
    District: District 3

    Contracts (2) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97687 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Route 110 (Littleton Road) at Tadmuck Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/10/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/03/2012
    Project Initiation Form PIF Entered 07/03/2012
    Project Initiation Form PRC Submitted 07/18/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/03/2016
    Project Management
    100% Design 100% Package Received 03/11/2016
    100% Design 100% Package Comments to DE 04/25/2016
    25% Design 25% Package Received 09/05/2014
    25% Design 25% Package Received 04/09/2015
    25% Design 25% Package Received 06/12/2015
    25% Design 25% Package Comments to DE 12/18/2014
    25% Design 25% Package Comments to DE 09/17/2015
    25% Design Design Public Hearing 11/04/2015
    75% Design 75% Package Received 12/04/2015
    75% Design 75% Package Comments to DE 01/21/2016
    Final Design PS&E Received 05/31/2016
    Final Design PS&E to Peer Reviewer 05/31/2016
    Final Design Peer Review Comments to DE 06/07/2016
    Final Design PS&E Received - Resub 1 07/18/2016