Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GARDNER- RESURFACING & RELATED WORK ON MATTHEW STREET
The project involves resurfacing and related work on Matthew Street, from Green Street to Route 140.
Location:
  • City of Gardner
  • Construction Begins: Summer 2017
    Resident Engineer: Ryan Davison
    Construction Bid Price: $946,609.17
    District: District 3

    Contracts (1) Progress
    # 98934 -- Construction Contract
    Resurfacing and Related Work along Mathews Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/02/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/03/2012
    Project Initiation Form PIF Entered 07/03/2012
    Project Initiation Form PRC Submitted 07/18/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 11/26/2016
    Project Management
    100% Design 100% Package Received 06/23/2015
    100% Design 100% Package Received 05/26/2016
    100% Design 100% Package Comments to DE 07/01/2016
    25% Design Design Public Hearing 07/13/2016
    75% Design 75% Package Received 09/04/2013
    75% Design 75% Package Comments to DE 11/04/2013
    Final Design PS&E Received 08/30/2016
    Final Design PS&E to FAPRO 11/09/2016
    Final Design PS&E Received - Resub 2 09/27/2016
    Final Design PS&E Received - Resub 3 09/30/2016