ERVING- STREETSCAPE & PEDESTRIAN IMPROVEMENTS ON ROUTE 63, FROM RIVER STREET TO 1,200 FT. NORTH OF LILLIAN WAY (1 MILE)
This project will consist of streetscape improvements and the construction and repair of sidewalks and wheelchair ramps. Additional work will include the installation of pedestrian level lighting, landscaping elements, street furniture and signage.
Location:
  • Town of Erving
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Jay Niedbala
    Construction Bid Price: $928,135.00
    District: District 2

    Contracts (2) Progress
    # 105778 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 63 (Lester and Moore Streets, Northfield Road) Completed
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/21/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/03/2012
    Project Initiation Form PIF Entered 07/03/2012
    Project Initiation Form PRC Submitted 07/03/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 01/26/2018
    100% Design 100% Package Comments to DE 03/06/2018
    25% Design 25% Package Received 12/08/2016
    25% Design 25% Package Comments to DE 02/13/2017
    25% Design 25% Package Received - Resub 1 08/18/2017
    25% Design Design Public Hearing 10/26/2017
    75% Design 75% Package Received 01/26/2018
    75% Design 75% Package Comments to DE 03/06/2018
    Final Design PS&E Received 06/14/2018
    Final Design Peer Review Comments to DE 05/23/2018
    Final Design PS&E Received - Resub 1 08/09/2018