Project Description:
WILLIAMSTOWN- MOHAWK BICYCLE/PEDESTRIAN TRAIL CONSTRUCTION
This proposed off-road bike/ped path would connect Route 7 (near Syndicate Rd) to Route 2 (near Galvin Rd). The preferred alignment for the path roughly follows the southern bank of the Hoosic River. The proposed cross-section would consist of a 10-ft wide paved surface with 2-ft graded shoulders on each side. The existing terrain consists of open fields, 100-yr floodplain, some wetlands, and out-lying suburban areas.
Location:
  • Town of Williamstown
  • Construction Begins: Autumn 2020
    Resident Engineer: Michael Wall
    Construction Bid Price: $5,036,515.80
    District: District 1

    Contracts (5) Progress
    # 112986 -- Construction Contract
    Construction of a Shared Use Path (Mohawk Bicycle / Pedestrian Trail) including Pedestrian Bridge (Pre-Fabricated Steel Truss) Br. No. W-37-038 over the Green River Completed
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77954 -- Design -- Planning Studies
    Mohawk Trail Scenic Byway Bicycle & Pedestrian Trail Planning, Phase II Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/08/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/03/2012
    Project Initiation Form PIF Entered 07/19/2012
    Project Initiation Form PRC Submitted 07/19/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/19/2020
    Project Management
    100% Design 100% Package Received 06/21/2019
    100% Design 100% Package Comments to DE 08/28/2019
    100% Design 100% Package Received - Resub 1 12/19/2019
    25% Design 25% Package Received 05/30/2017
    25% Design 25% Package Received 06/18/2018
    25% Design 25% Package Comments to DE 09/29/2017
    75% Design 75% Package Received 12/05/2018
    Final Design PS&E Received 08/28/2020
    Final Design PS&E to FAPRO 09/07/2020