Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOLYOKE- RESURFACING & RELATED WORK ON HERITAGE STREET, FRONT STREET & DWIGHT STREET FROM MAPLE ST TO THE 1ST LEVEL CANAL (.54 MILES)
This project includes roadway resurfacing on a portion of Dwight Street from Maple Street to the 1st Level Canal and utility improvements, pedestrian enhancements, and related work along Front Street, Heritage Street and Dwight Street.
Location:
  • City of Holyoke
  • Construction Begins: Spring 2019
    Resident Engineer: Todd Moylan
    Construction Bid Price: $3,596,765.75
    District: District 2

    Contracts (1) Progress
    # 105938 -- Construction Contract
    Roadway Reconstruction and Related Work on Dwight, Front and Heritage Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/09/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/06/2012
    Project Initiation Form PIF Entered 07/06/2012
    Project Initiation Form PRC Submitted 07/10/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 05/07/2018
    100% Design 100% Package Comments to DE 07/02/2018
    25% Design 25% Package Received 10/11/2013
    25% Design 25% Package Received 03/19/2015
    25% Design 25% Package Received 05/19/2016
    25% Design 25% Package Comments to DE 04/25/2014
    25% Design 25% Package Comments to DE 06/02/2015
    25% Design 25% Package Approved 06/09/2016
    25% Design Design Public Hearing 07/20/2016
    75% Design 75% Package Received 01/26/2018
    75% Design 75% Package Comments to DE 03/05/2018
    Final Design PS&E Received 08/13/2018
    Final Design PS&E to Peer Reviewer 08/13/2018
    Final Design Peer Review Comments to DE 08/20/2018
    Final Design PS&E Received - Resub 1 08/27/2018