Project Description:
BARNSTABLE- BOURNE- SANDWICH- INSTALLATION OF REAL TIME TRAFFIC MONITORING (RTTM) SYSTEM AND VARIABLE MESSAGE BOARDS ON ROUTES 6, 25 AND 28 (CAPE COD REGIONAL ITS)
Work consists of installing permanent Intelligent Transportation System (ITS) equipment to capture real time data and provide this information to the traveling public to and from Cape Cod on new hybrid travel time signs.
Location:
  • Town of Barnstable
  • Town of Bourne
  • Town of Sandwich
  • Resident Engineer: Cassandra Asvestas
    Construction Contract Value: $1,301,768.88
    Construction Bid Price: $1,144,444.44
    Initial Construction Estimate: $1,108,245.00
    District: District 5

    Contracts (1) Progress
    # 79288 -- Construction Contract
    Installation of Real Time Traffic Monitoring (RTTM) System and Variable Message Boards along Sections of Route 6, 25 and 28. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/04/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/17/2012
    Project Initiation Form PIF Entered 07/17/2012
    Project Initiation Form PRC Submitted 07/17/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/17/2013
    Project Management
    100% Design 100% Package Received 05/28/2013
    75% Design 75% Package Received 02/11/2013
    Final Design PS&E Received 08/06/2013
    Final Design PS&E to FAPRO 08/06/2013