Project Description:
FRANKLIN- PEDESTRIAN BRIDGE CONSTRUCTION, F-08-005, OLD SR 140 OVER MBTA/CSX
Bridge F-08-005 is closed because Route 140 has been re-aligned. A new bridge has taken its place. This bridge is structurally deficient with an AASHTO = 15.5. It is proposed to demolish the old roadway bridge and replace it with a pedestrian bridge.
Location:
  • Town of Franklin
  • Resident Engineer: Anthony Tavalone
    Construction Bid Price: $1,199,465.15
    District: District 3

    Contracts (3) Progress
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90405 -- Construction Contract
    Bridge Replacement Br. No. F-08-005 (Pre-Fab Steel Truss) West Central Street over the MBTA and CSX Railroads. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/23/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/25/2012
    Project Initiation Form PIF Entered 07/25/2012
    Project Initiation Form PRC Submitted 07/25/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 08/29/2015
    Project Management
    100% Design 100% Package Received 06/29/2015
    100% Design 100% Package Comments to DE 07/23/2015
    100% Design 100% Plans Approved 07/24/2015
    100% Design 100% Plans Complete 07/01/2015
    25% Design 25% Package Received 11/03/2014
    25% Design 25% Package Comments to DE 01/26/2015
    25% Design 25% Package Comments to DE 04/30/2015
    25% Design Design Public Hearing 04/06/2015
    75% Design 75% Package Received 04/27/2015
    75% Design 75% Package Comments to DE 06/01/2015
    Final Design PS&E Received 08/17/2015
    Final Design PS&E to FAPRO 08/26/2015
    Consultant Contract Process NTP Issued 04/08/2014