BOSTON- SPECTACLE ISLAND LATENT DEFECT REPAIRS
Repairs to the Spectacle Island Leachate Collection System on South Drumlin in accordance with DEP Correspondence date June 14, 2012
Location:
  • City of Boston
  • Resident Engineer: Daniel Stiven
    Construction Contract Value: $285,430.00
    Construction Bid Price: $258,430.00
    Initial Construction Estimate: $130,646.25
    District: District 6

    Contracts (1) Progress
    # 68122 -- Construction Contract
    Spectacle Island Leachate Collection Pipe Repairs. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/21/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/21/2012
    Project Initiation Form PIF Entered 08/21/2012
    Project Initiation Form PRC Submitted 08/29/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 02/02/2013
    Project Management
    Final Design PS&E Received 01/25/2013
    Final Design PS&E to FAPRO 01/29/2013