BRAINTREE- CONSTRUCTION OF NEW MASSDOT SIGN SHOP AT MAINTENANCE DEPOT
Work will consist of relocating the Medford Sign Shop to a proposed new building at the Braintree Depot.
Location:
  • Town of Braintree
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Edmond Libsch
    Estimated Total Contract Cost: $12,298,910.75
    Estimated Total Federal Participating Construction Cost: N/A
    Current Status: 100% Package Received (as of 06/10/2015 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/13/2012
    Project Initiation Form PIF Received 08/01/2012
    Project Initiation Form PIF Entered 08/27/2012
    Project Initiation Form PRC Submitted 08/27/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Management
    100% Design 100% Package Received 06/10/2015
    25% Design 25% Package Received 01/15/2014
    75% Design 75% Plans Complete 12/15/2014