| Project Description: |
DISTRICT 3- SIGNS & MARKING UPGRADES FOR STOP-SIGN CONTROLLED INTERSECTIONS AT VARIOUS LOCATIONS
FHWA identified systematic low cost fixes at stop-controlled intersections as a means to dramatically reduce crashes. There are 20 communities with a total of 60 intersections.
|
| Location: | |
| Resident Engineer: | Peter Kurt![]() |
| Construction Contract Value: | $144,409.00 |
| Construction Bid Price: | $116,190.76 |
| Initial Construction Estimate: | $150,621.50 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||