Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DARTMOUTH- INTERSECTION IMPROVEMENTS & RELATED WORK AT CHASE ROAD & OLD WESTPORT ROAD
This project proposal is a response to ongoing safety issues and a lack of multi-modal accommodation at the approaches to the intersection of Chase Road and Old Westport Road. Full signalization of the intersection is planned in addition to the construction of new sidewalks and realignment of pavement markings to provide bike accommodating paved shoulders.
Location:
  • Town of Dartmouth
  • Construction Begins: Autumn 2018
    Resident Engineer: Alex Lustikman
    Construction Bid Price: $677,646.50
    District: District 5

    Contracts (1) Progress
    # 103961 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Chase and Old Westport Roads Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/28/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/06/2012
    Project Initiation Form PIF Entered 01/09/2013
    Project Initiation Form PRC Submitted 01/09/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 05/12/2018
    Project Management
    100% Design 100% Package Received 09/01/2017
    100% Design 100% Package Comments to DE 11/01/2017
    25% Design 25% Package Received 03/18/2016
    25% Design 25% Package Comments to DE 09/27/2016
    25% Design Design Public Hearing 02/23/2017
    75% Design 75% Package Received 09/01/2017
    Final Design PS&E Received 02/08/2018
    Final Design PS&E to Peer Reviewer 02/15/2018
    Final Design Peer Review Comments to DE 02/27/2018
    Final Design PS&E Received - Resub 1 03/28/2018