Project Description:
NATICK- BRIDGE REPLACEMENT, N-03-003, MARION STREET OVER THE MBTA RAILROAD
Bridge N-03-003 was closed by MassDOT on 8-14-2012 due to settlement of the composite concrete/closed grating deck. The existing Pony Truss structure was originally built in 1896 and has had two major rehabilitations in the past 24 years.
Location:
  • Town of Natick
  • Resident Engineer: Nitin Patel
    Construction Contract Value: $3,668,530.00
    Construction Bid Price: $2,752,547.83
    Initial Construction Estimate: $2,666,000.00
    District: District 3

    Contracts (4) Progress
    # 69759 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86302 -- Construction Contract
    Bridge Replacement Br. No. N-03-003 (Steel) Marion Street over the MBTA Railroad. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/01/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/25/2012
    Project Initiation Form PIF Entered 09/25/2012
    Project Initiation Form PRC Submitted 09/25/2012
    Project Review Committee PRC Approved 01/04/2013
    Project Status Advertised 01/10/2015
    Project Management
    100% Design 100% Package Received 11/13/2014
    100% Design 100% Package Comments to DE 12/05/2014
    25% Design 25% Package Received 05/12/2014
    25% Design 25% Package Received 09/19/2014
    25% Design 25% Package Comments to DE 06/04/2014
    25% Design 25% Package Comments to DE 09/23/2014
    25% Design Design Public Hearing 10/07/2014
    Final Design PS&E Received 12/12/2014
    Final Design PS&E Received 06/03/2015
    Final Design PS&E to FAPRO 01/07/2015