Project Description:
REHOBOTH- EMERGENCY REPAIR OF CULVERT R-04-002 ON WHEELER STREET
This project is intended to address the need for emergency repairs to a municipally owned culvert, headwalls, guardrail, roadway embankment and asphalt roadway as a result of heavy rains and floodwater occuring the Spring season of 2010.
Location:
  • Town of Rehoboth
  • Resident Engineer: Roderick Jackson
    Construction Contract Value: $1,772,496.50
    Construction Bid Price: $1,600,015.00
    Initial Construction Estimate: $1,387,000.00
    District: District 5

    Contracts (2) Progress
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 86467 -- Construction Contract
    Bridge Replacement Br. No. R-04-002 (Precast Concrete Arch) Wheeler Street over the Palmer River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/27/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: EMERGENCY RELIEF
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/28/2012
    Project Initiation Form PIF Entered 10/02/2012
    Project Initiation Form PRC Submitted 10/02/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 01/24/2015
    Project Management
    100% Design 100% Package Received 09/25/2014
    100% Design 100% Package Comments to DE 11/06/2014
    25% Design 25% Package Received 12/09/2013
    25% Design 25% Package Comments to DE 06/02/2014
    Final Design PS&E Received 12/09/2014
    Final Design PS&E to FAPRO 01/21/2015