Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- FORT POINT CHANNEL WATER TRANSPORTATION FACILITY CONSTRUCTION
The Fort Point Channel Ferry Facility (FPCFF) is a CA/T Project mitigation measure required to support development of Boston’s water transport system. The FPCFF is to provide ADA-accessible, public ferry service and public landing benefits for the westerly side of the Fort Point Channel. The project has been delayed for a variety of reasons, until recently because of conflicts with adjacent Transitway and private construction activities along with the Old Northern Avenue Bridge (ONA Bridge). The construction of this project is complex due to low clearance under the bridges along the channel and operational constraints. The project consists of the construction of a fixed timber and steel multi-level deck and a floating barge system with ADA compliant ramps.
Location:
  • City of Boston
  • Resident Engineer: Ryan Johnson
    Construction Contract Value: $3,354,087.00
    Construction Bid Price: $2,913,380.20
    Initial Construction Estimate: $2,378,385.07
    District: District 6

    Contracts (5) Progress
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64319 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 80542 -- Construction Contract
    Construction of the Fort Point Channel Water Transportation Facility. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/15/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/03/2012
    Project Initiation Form PIF Entered 10/03/2012
    Project Initiation Form PRC Submitted 10/03/2012
    Project Review Committee PRC Approved 10/25/2012
    Project Status Advertised 11/16/2013
    Project Management
    100% Design 100% Package Received 06/04/2013
    Final Design PS&E Received 11/07/2013
    Final Design PS&E Received 09/04/2015
    Final Design PS&E to FAPRO 11/12/2013
    Final Design PS&E Received - Resub 1 09/09/2016
    Consultant Contract Process Scope to DE 10/25/2012
    Consultant Contract Process NTP Issued 04/17/2013