Project Description: |
TEMPLETON- RESURFACING & RELATED WORK ON A SECTION OF ROUTE 68, FROM THE GARDNER C.L. TO THE END OF STATE HIGHWAY
Project consists of milling and resurfacing a 2.0 mile section of State Road (Rte. 68) in the Town of Templeton. Also included will be sidewalk and wheelchair ramp reconstruction, reset granite curb, minor pavement widening, new pavement markings and new signage.
|
Location: |
|
Construction Begins: | Spring 2017 |
Resident Engineer: | Matthew Fuller |
Construction Bid Price: | $1,794,345.12 |
District: | District 2 |
|
Bridges |
|
|
|
|