TEMPLETON- RESURFACING & RELATED WORK ON A SECTION OF ROUTE 68, FROM THE GARDNER C.L. TO THE END OF STATE HIGHWAY
Project consists of milling and resurfacing a 2.0 mile section of State Road (Rte. 68) in the Town of Templeton. Also included will be sidewalk and wheelchair ramp reconstruction, reset granite curb, minor pavement widening, new pavement markings and new signage.
Location:
  • Town of Templeton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Lyris Liautaud
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.