Project Description:
TEMPLETON- RESURFACING & RELATED WORK ON A SECTION OF ROUTE 68, FROM THE GARDNER C.L. TO THE END OF STATE HIGHWAY
Project consists of milling and resurfacing a 2.0 mile section of State Road (Rte. 68) in the Town of Templeton. Also included will be sidewalk and wheelchair ramp reconstruction, reset granite curb, minor pavement widening, new pavement markings and new signage.
Location:
  • Town of Templeton
  • Construction Begins: Spring 2017
    Resident Engineer: Matthew Fuller
    Construction Bid Price: $1,794,345.12
    District: District 2

    Contracts (1) Progress
    # 97844 -- Construction Contract
    Resurfacing and Related Work (Including Signals) along a Section of Route 68 (State Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/07/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2012
    Project Initiation Form PIF Entered 03/12/2013
    Project Initiation Form PRC Submitted 03/12/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 09/17/2016
    Project Management
    100% Design 100% Package Received 08/22/2016
    100% Design 100% Package Comments to DE 09/09/2016
    25% Design 25% Package Received 03/05/2015
    25% Design 25% Package Comments to DE 03/30/2015
    25% Design 25% Package Comments to DE 08/01/2016
    75% Design 75% Package Received 03/05/2015
    75% Design 75% Package Comments to DE 03/30/2015
    75% Design 75% Package Comments to DE 08/01/2016
    Final Design PS&E Received 08/22/2016
    Final Design Peer Review Comments to DE 09/09/2016
    Final Design PS&E to FAPRO 09/12/2016