Project Description:
WILMINGTON- BRIDGE REPLACEMENT, W-38-002, ROUTE 38 (MAIN STREET) OVER MBTA RAILROAD
A 3 day weekend closure is recommended for this project since this route is used by school bus and emergency vehicles.
Location:
  • Town of Wilmington
  • Construction Begins: Autumn 2023
    Resident Engineer: Brian Polley
    Construction Bid Price: $11,837,354.40
    District: District 4
    Current Status: Field office is set up. Survey party on site to lay out baseline, easement limits, clearing and grubbing limits and new telephone pole locations. (as of 12/12/2023)

    Contracts (2) Progress
    # 122687 -- Construction Contract
    Bridge Replacement, W-38-002, Route 38 (Main Street) over MBTA Railroad 1% Complete
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/05/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Field office is set up. Survey party on site to lay out baseline, easement limits, clearing and grubbing limits and new telephone pole locations.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/23/2012
    Project Initiation Form PIF Entered 10/23/2012
    Project Initiation Form PRC Submitted 10/25/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 07/01/2023
    Project Management
    100% Design 100% Package Received 11/18/2022
    100% Design 100% Package Comments to DE 12/28/2022
    25% Design 25% Package Received 11/20/2020
    25% Design 25% Package Comments to DE 03/08/2021
    25% Design 25% Package Comments to DE 03/08/2021
    25% Design Design Public Hearing 12/15/2021
    75% Design 75% Package Received 04/29/2022
    75% Design 75% Package Comments to DE 06/08/2022
    Final Design PS&E Received 04/04/2023
    Final Design PS&E Received - Resub 1 06/07/2023
    Final Design PS&E Received - Resub 2 06/15/2023