Project Description:
MILTON- DECK RECONSTRUCTION OVER SE EXPRESSWAY (EAST MILTON SQUARE), INCLUDES PARKING & NEW LANDSCAPED AREA
This project involves the redesign of the current deck built over the SE Xpressway in Milton. The town hopes to utilize this space first to add additional parking and make the existing space more attractive. There is currently a parking shortage for the business in East Milton Square. The additional parking contributes to an economic development advantage.
Location:
  • Town of Milton
  • Construction Begins: Spring 2020
    Resident Engineer: Laura Montiel
    Construction Bid Price: $6,849,943.00
    District: District 6

    Contracts (2) Progress
    # 109299 -- Construction Contract
    East Milton Square Bridge Deck Reconstruction (Including Signals & Landscaping) Br. No. M-25-021 (Concrete) 6 Adjacent Streets all over Interstate 93 Completed
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/09/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/25/2012
    Project Initiation Form PIF Entered 10/25/2012
    Project Initiation Form PRC Submitted 10/25/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 08/10/2019
    Project Management
    100% Design 100% Package Received 06/10/2019
    25% Design 25% Package Received 12/19/2014
    25% Design 25% Package Comments to DE 11/27/2018
    25% Design Design Public Hearing 09/09/2015
    75% Design 75% Package Received 12/19/2018
    75% Design 75% Package Comments to DE 01/23/2019
    Final Design PS&E Received 09/12/2019
    Final Design PS&E to FAPRO 07/29/2019