PEMBROKE- INTERSECTION IMPROVEMENTS AND RELATED WORK AT WASHINGTON STREET (ROUTE 53) AND PLEASANT STREET
This project is intended to address ongoing safety issues and a lack of bicycle and pedestrian accommodation through the installation of traffic signals, left turn lanes, minor widening to provide minimal bike accommodating shoulders and a sidewalk on the East side of Washington Street (Route 53).
Location:
  • Town of Pembroke
  • Construction Begins: Autumn 2018
    Resident Engineer: Russell Davis
    Construction Bid Price: $1,680,882.60
    District: District 5

    Contracts (1) Progress
    # 103490 -- Construction Contract
    Intersection Improvements and Related Work at Washington (Route 53) and Pleasant Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/27/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2012
    Project Initiation Form PIF Entered 11/02/2012
    Project Initiation Form PRC Submitted 11/02/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 03/17/2018
    Project Management
    100% Design 100% Package Received 07/07/2016
    100% Design 100% Package Comments to DE 08/15/2016
    100% Design 100% Plans Approved 08/15/2016
    25% Design 25% Package Received 12/03/2013
    25% Design 25% Package Comments to DE 02/26/2014
    25% Design Design Public Hearing 09/30/2015
    75% Design 75% Package Received 12/14/2015
    75% Design 75% Package Comments to DE 12/18/2015
    75% Design 75% Plans Approved 01/26/2016
    75% Design 75% Plans Complete 01/26/2016
    Final Design PS&E Received 11/07/2017
    Final Design PS&E to Peer Reviewer 06/13/2017
    Final Design Peer Review Comments to DE 06/20/2017
    Final Design PS&E to FAPRO 03/12/2018