Project Description:
ATTLEBORO- INTERSECTION IMPROVEMENTS AT ROUTE 1 (WASHINGTON STREET)/ROUTE 1A (NEWPORT AVENUE) AND ROUTE 123 (HIGHLAND AVENUE)
Work on this project includes traffic signal upgrades, geometric improvements and improved bicycle and pedestrian accommodation at the Routes 1/1A/123 intersections.
Location:
  • City of Attleboro
  • Construction Begins: Autumn 2022
    Resident Engineer: Eric Borman
    Construction Bid Price: $7,315,869.60
    District: District 5
    Current Status: R.M. Pacella: Drainage, box widening, curbing, concrete sidewalk, and traffic signal conduit Rte. 1A. Verizon: Overhead relocation operation. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 10/29/2024)
    Additional Info: Temporary lane taking with traffic control/direction provided by police details. (as of 10/29/2024)

    Contracts (5) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 120188 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Route 1 (Washington Street) and Route 1A (Newport Avenue) at Route 123 (Highland Avenue) 25% Complete
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/14/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2012
    Project Initiation Form PIF Entered 11/06/2012
    Project Initiation Form PRC Submitted 11/06/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 12/23/2020
    100% Design 100% Package Rejected 12/24/2020
    100% Design 100% Package Received - Resub 1 01/06/2021
    25% Design 25% Package Received 01/28/2016
    25% Design 25% Package Comments to DE 06/02/2016
    25% Design Design Public Hearing 03/19/2018
    75% Design 75% Package Received 03/19/2020
    75% Design 75% Package Comments to DE 07/27/2020
    Final Design PS&E Received 07/08/2022
    Final Design PS&E Received - Resub 1 08/01/2022