Project Description:
ATTLEBORO- INTERSECTION IMPROVEMENTS AT ROUTE 1 (WASHINGTON STREET)/ROUTE 1A (NEWPORT AVENUE) AND ROUTE 123 (HIGHLAND AVENUE)
Work on this project includes traffic signal upgrades, geometric improvements and improved bicycle and pedestrian accommodation at the Routes 1/1A/123 intersections.
Location:
  • City of Attleboro
  • Construction Begins: Autumn 2022
    Resident Engineer: Eric Borman
    Construction Bid Price: $7,315,869.60
    District: District 5

    Contracts (5) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 120188 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Route 1 (Washington Street) and Route 1A (Newport Avenue) at Route 123 (Highland Avenue)
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/14/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2012
    Project Initiation Form PIF Entered 11/06/2012
    Project Initiation Form PRC Submitted 11/06/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 12/23/2020
    100% Design 100% Package Rejected 12/24/2020
    100% Design 100% Package Received - Resub 1 01/06/2021
    25% Design 25% Package Received 01/28/2016
    25% Design 25% Package Comments to DE 06/02/2016
    25% Design Design Public Hearing 03/19/2018
    75% Design 75% Package Received 03/19/2020
    75% Design 75% Package Comments to DE 07/27/2020
    Final Design PS&E Received 07/08/2022
    Final Design PS&E Received - Resub 1 08/01/2022