Project Description:
COHASSET- SUPERSTRUCTURE REPLACEMENT & SUBSTRUCTURE REHABILITATION, C-17-002, ATLANTIC AVENUE OVER LITTLE HARBOR INLET
This project is intended to rehabilitate and replace a structurally deficient bridge in Cohasset located on Atlantic Avenue over Little Harbor Inlet.
Location:
  • Town of Cohasset
  • Construction Begins: Spring 2017
    Resident Engineer: Peter Benkart
    Construction Bid Price: $6,247,362.50
    District: District 5

    Contracts (3) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97837 -- Construction Contract
    Bridge Replacement Br. No. C-17-002 (Pre-Cast NEBT Beams) Atlantic Avenue over Little Harbor Inlet. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/26/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/07/2012
    Project Initiation Form PIF Entered 11/07/2012
    Project Initiation Form PRC Submitted 11/08/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 09/17/2016
    Project Management
    100% Design 100% Package Received 05/22/2017
    25% Design 25% Package Received 10/21/2015
    25% Design 25% Package Comments to DE 03/10/2016
    25% Design Design Public Hearing 02/25/2016
    75% Design 75% Package Received 06/24/2016
    75% Design 75% Package Comments to DE 07/28/2016
    Final Design PS&E Received 08/23/2016
    Final Design PS&E to Peer Reviewer 09/06/2016
    Final Design Peer Review Comments to DE 09/20/2016
    Final Design PS&E to FAPRO 09/12/2016
    Final Design PS&E Received - Resub 1 10/11/2016
    Consultant Contract Process NTP Issued 11/19/2014