| Project Description: |
NORWELL- PEMBROKE- MARSHFIELD- BRIDGE REPLACEMENT, N-24-004=P-05-008, ROUTE 3 (NB & SB) OVER NORTH RIVER
This project is intended to replace a structurally deficient bridge on Route 3 in Norwell, Pembroke and Marshfield over the North River.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Autumn 2026 |
| Project Manager: | Eamon Kernan![]() |
| Estimated Total Contract Cost: | $120,987,128.40 |
| Estimated Total Federal Participating Construction Cost: | $126,019,901.70 |
| Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the STATEWIDE. |
| District: | District 5 |
| Current Status: | 25% Package Received - Resub 1 (as of 11/21/2025 ) |
|
Bridges
|
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||