Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORWELL- PEMBROKE- MARSHFIELD- BRIDGE REPLACEMENT, N-24-004=P-05-008, ROUTE 3 (NB & SB) OVER NORTH RIVER
This project is intended to replace a structurally deficient bridge on Route 3 in Norwell, Pembroke and Marshfield over the North River.
Location:
  • Town of Marshfield
  • Town of Norwell
  • Town of Pembroke
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Eamon Kernan
    Estimated Total Contract Cost: $114,907,306.50
    Estimated Total Federal Participating Construction Cost: $119,564,105.00
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 07/11/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/07/2012
    Project Initiation Form PIF Entered 11/07/2012
    Project Initiation Form PRC Submitted 11/08/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 07/11/2026
    Project Management
    25% Design 25% Package Received 05/22/2025
    25% Design 25% Package Received 06/04/2026
    25% Design 25% Package Comments to DE 07/22/2025
    25% Design 25% Package Comments to DE 07/23/2025
    25% Design 25% Package Comments to DE 12/21/2025
    25% Design 25% Package Received - Resub 1 11/21/2025
    25% Design Design Public Hearing 01/21/2026
    Final Design PS&E Received 03/05/2026
    Final Design PS&E Received - Resub 1 06/04/2026
    Final Design PS&E Received - Resub 2 07/09/2026
    Consultant Contract Process NTP Issued 08/30/2022