Project Description:
DISTRICT 6- INSTALLATION OR REHABILITATION OF BRIDGE DRAINAGE SYSTEMS AT VARIOUS LOCATIONS
Project provides a way for the District Office to direct the undertaking of repair or installations of new drainage systems at various locations throughout the District.
Location:
Resident Engineer: Matthew Cahill
Construction Contract Value: $1,386,962.50
Construction Bid Price: $989,462.50
Initial Construction Estimate: $958,080.00
District: District 6

Contracts (1) Progress
# 77598 -- Construction Contract
Bridge Drainage Repairs and Improvements at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/05/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/08/2012
    Project Initiation Form PIF Entered 11/08/2012
    Project Initiation Form PRC Submitted 11/08/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 05/18/2013
    Project Management
    Final Design PS&E Received 04/17/2013
    Final Design PS&E to FAPRO 05/15/2013