Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- HAZARDOUS TREE REMOVAL & TRIMMING (AREA D)
Contract provides a mechanism for the district to address dead or dying trees in a scheduled or emergency fashion. Contract also provides for side line trimming.
Location:
Resident Engineer: Malcolm Lavalley
Construction Contract Value: $618,965.50
Construction Bid Price: $487,565.50
Initial Construction Estimate: $529,600.00
District: District 5

Contracts (1) Progress
# 77279 -- Construction Contract
Scheduled and Emergency Selective Clearing and Tree Removal at Various Locations in Area D. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/18/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/26/2012
    Project Initiation Form PIF Entered 12/08/2012
    Project Initiation Form PRC Submitted 12/03/2012
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 04/20/2013
    Project Management
    Final Design PS&E Received 01/22/2013
    Final Design PS&E to FAPRO 04/16/2013