Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 3- SCHEDULED & EMERGENCY BRIDGE DECK REPAIR AT VARIOUS LOCATIONS
any deck element (joints, parapets, wearing surface, etc) requiring a repair, will be repaired under this contract.
Location:
Resident Engineer: Marghrit Arous
Construction Contract Value: $3,996,632.00
Construction Bid Price: $989,632.00
Initial Construction Estimate: $1,540,000.00
District: District 3

Contracts (1) Progress
# 77895 -- Construction Contract
Scheduled and Emergency Bridge Deck Repairs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/01/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/21/2013
    Project Initiation Form PIF Entered 01/21/2013
    Project Initiation Form PRC Submitted 01/21/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 06/15/2013
    Project Management
    Final Design PS&E Received 05/14/2013
    Final Design PS&E to FAPRO 06/11/2013