Project Description:
SEEKONK- INTERSECTION IMPROVEMENTS & RELATED WORK AT FALL RIVER AVENUE (ROUTE 114A) AND COUNTY STREET
This project is intended to address ongoing capacity constraints and a lack of adequate pedestrian facilities at the intersection. The intersection lacks adequate capacity to process 24,000 vehicles daily. Both the NB and SB Fall River Avenue approaches to County Street and the County Street EB approach to Fall River Avenue need dedicated left turn lanes with appropriate signal phasing. In addition, the construction of refuge lanes on the Fall River Avenue approaches to County Street are proposed. Also, sidewalks and crosswalks need rehabilitation and pedestrian activated traffic signals are proposed.
Location:
  • Town of Seekonk
  • Construction Begins: Autumn 2019
    Resident Engineer: Marc Cardinal
    Construction Bid Price: $2,033,446.58
    District: District 5

    Contracts (1) Progress
    # 107786 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Fall River Avenue (Route 114A) at County Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/06/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2013
    Project Initiation Form PIF Entered 02/13/2013
    Project Initiation Form PRC Submitted 02/13/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 05/18/2019
    Project Management
    100% Design 100% Package Received 02/08/2019
    25% Design 25% Package Received 02/09/2015
    25% Design 25% Package Comments to DE 12/29/2015
    25% Design Design Public Hearing 06/09/2016
    75% Design 75% Package Received 02/26/2018
    75% Design 75% Package Comments to DE 05/08/2018
    Final Design PS&E Received 04/26/2019
    Final Design PS&E to FAPRO 05/06/2019