Project Description:
BOSTON- BOAT WALL REHABILITATION & MISCELLANEOUS REPAIRS IN I-93/I-90 CA/T (CRC 9)
Approved Trust Fund Project CRC-9, (construction contract remediation). The project involves remediation of the issues raised in the Stem To Strern Report for the Boat wall section of I-90. This includes an extensive scope of work which has been saved on the document tab. Including the silane sealing of the exposed surfaces, TS7 CIP wall delineations, CV3 spall on box girders, miscellaneous steel viaduct repairs, SV12 crack in weld LC-N, ZB15 Missing nut in floor beam, missing transverse tendons, supply duck shotcrete repair at VB 3, concrete repair I-93, ZB21 Electical Tape, and railing at ramp L.
Location:
  • City of Boston
  • Resident Engineer: Jeovanny Rodriguez
    Construction Bid Price: $5,489,308.00
    District: District 6

    Contracts (3) Progress
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86981 -- Construction Contract
    Concrete Repairs and Related Work along Boat Sections of Interstates 90 & 93 and Central Artery Tunnel System Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/02/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/01/2013
    Project Initiation Form PIF Entered 02/01/2013
    Project Initiation Form PRC Submitted 11/03/2014
    Project Review Committee PRC Approved 11/25/2014
    Project Status Advertised 03/14/2015
    Project Management
    100% Design 100% Package Received 02/20/2015
    Final Design PS&E Received 03/03/2015
    Final Design PS&E to FAPRO 03/04/2015