Project Description:
|
BOSTON- BOAT WALL REHABILITATION & MISCELLANEOUS REPAIRS IN I-93/I-90 CA/T (CRC 9)
Approved Trust Fund Project CRC-9, (construction contract remediation). The project involves remediation of the issues raised in the Stem To Strern Report for the Boat wall section of I-90. This includes an extensive scope of work which has been saved on the document tab. Including the silane sealing of the exposed surfaces, TS7 CIP wall delineations, CV3 spall on box girders, miscellaneous steel viaduct repairs, SV12 crack in weld LC-N, ZB15 Missing nut in floor beam, missing transverse tendons, supply duck shotcrete repair at VB 3, concrete repair I-93, ZB21 Electical Tape, and railing at ramp L.
|