Project Description:
WELLFLEET- INTERSECTION IMPROVEMENTS & RELATED WORK AT ROUTE 6 & MAIN STREET
The intent of this project is to provide safety upgrades and improved accommodation for all modes of travel. Work on this project includes intersection improvements and the installation of bike lanes and sidewalks. Also included is pavement milling and overlay, drainage upgrades and the installation of new pavement markings and signs.
Location:
  • Town of Wellfleet
  • Construction Begins: Autumn 2023
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $14,390,933.85
    District: District 5
    Current Status: Lawrence Lynch continues installing drainage structures throughout project site. Contractor also installing underground utility conduit. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/22/2024)

    Contracts (4) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 122609 -- Construction Contract
    Intersection Improvements & Related Work at Route 6 & Main Street 13% Complete
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/05/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Lawrence Lynch continues installing drainage structures throughout project site. Contractor also installing underground utility conduit. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2013
    Project Initiation Form PIF Entered 05/14/2013
    Project Initiation Form PRC Submitted 05/15/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 04/15/2022
    100% Design 100% Package Comments to DE 05/24/2022
    100% Design 100% Package Received - Resub 1 01/25/2023
    25% Design 25% Package Received 08/05/2020
    25% Design 25% Package Comments to DE 12/09/2020
    25% Design Design Public Hearing 09/22/2021
    75% Design 75% Package Received 12/22/2021
    75% Design 75% Package Comments to DE 02/01/2022
    Final Design PS&E Received 04/25/2023
    Final Design PS&E Received - Resub 1 06/08/2023
    Consultant Contract Process NTP Issued 06/28/2017