Project Description: |
CHELMSFORD- TRAFFIC SIGNAL INSTALLATION AT ROUTE 110 & ROUTE 495 (2 LOCATIONS)
This work consists of the installation of two traffic signals at the intersection of Route 495 and Route 110 (Exit 34). Also included is the addition of left turn lanes.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2027 |
Project Manager: | Jonathan E Freeman |
Estimated Total Contract Cost: | $7,299,768.05 |
Estimated Total Federal Participating Construction Cost: | $7,708,380.20 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 10/07/2022 ) |
|
Bridges |
|
|
|