Project Description:
STOUGHTON- CORRIDOR IMPROVEMENTS ON ROUTE 138, FROM 300 FEET NORTH OF CHARLES AVENUE TO LINCOLN STREET (PHASE 1)
This project is intended to address safety, congestion and a lack of multi-modal accommodation. Proposed improvements include roadway rehabilitation, construction of continuous sidewalks and curbing, restriping of the travel lanes to provide bike accommodating shoulders. Drainage upgrades, pavement markings and signs are also included.
Location:
  • Town of Stoughton
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Fedner Pierre
    Construction Bid Price: $8,725,969.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5

    Contracts (3) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123869 -- Construction Contract
    Corridor Improvements on Route 138, from 300 Feet North of Charles Avenue to Lincoln Street (Phase 1)
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/22/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: STOUGHTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; Total Cost is $17,404,332; Advance Construction (AC); AC Year 1 of 2 Expenditure in 2023 is $8,441,033; AC Year 2 of 2 Expenditure in 2024 is $8,963,299; TEC Score 51.78; Status is 100% Design
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $7,170,639.20
    State Cost: $1,792,659.80
    Total Cost: $8,963,299.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/12/2013
    Project Initiation Form PIF Entered 02/12/2013
    Project Initiation Form PRC Submitted 02/12/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 10/27/2022
    100% Design 100% Package Comments to DE 11/28/2022
    25% Design 25% Package Received 12/24/2018
    25% Design 25% Package Comments to DE 04/01/2019
    25% Design 25% Package Received - Resub 1 10/13/2020
    25% Design Design Public Hearing 02/16/2022
    75% Design 75% Package Received 04/19/2022
    75% Design 75% Package Comments to DE 06/21/2022
    Final Design PS&E Received 03/01/2023
    Final Design PS&E Received - Resub 1 04/07/2023
    Final Design PS&E Received - Resub 2 05/19/2023
    Final Design PS&E Received - Resub 3 07/20/2023