Project Description:
TISBURY- BIKE & PEDESTRIAN IMPROVEMENTS ALONG BEACH ROAD, FROM THE TERMINATION OF THE EXISTING SHARED USE PATH WESTERLY TO THE FIVE CORNERS INTERSECTION
This project is intended to provide improved on-road bicycle accommodation where feasible and off-road bike and pedestrian accommodation along Beach Road from the termination of the existing shared use path East of Wind's Up Marketplace Westerly to the 5-Corners intersection.
Location:
  • Town of Tisbury
  • Construction Begins: Spring 2020
    Resident Engineer: Michael King
    Construction Bid Price: $4,854,706.71
    District: District 5

    Contracts (5) Progress
    # 109550 -- Construction Contract
    Roadway Reconstruction and Shared Use Path Extension and Related Work along a Section of Beach Road Completed
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/20/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/20/2013
    Project Initiation Form PIF Entered 02/21/2013
    Project Initiation Form PRC Submitted 02/21/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/31/2019
    Project Management
    100% Design 100% Package Received 04/09/2018
    100% Design 100% Package Comments to DE 06/01/2018
    25% Design 25% Package Received 12/11/2015
    25% Design 25% Package Comments to DE 03/28/2016
    25% Design Design Public Hearing 09/14/2016
    75% Design 75% Package Received 02/03/2017
    75% Design 75% Package Comments to DE 04/28/2017
    Final Design PS&E Received 10/01/2018
    Final Design PS&E to FAPRO 08/19/2019
    Final Design PS&E Received - Resub 1 03/01/2019