TAUNTON- RECONSTRUCTION AND EXPANSION OF DISTRICT FIVE ADMINISTRATION BUILDING
RECONSTRUCTION OF DISTRICT FIVE ADMINISTRATION BLDG FOR EXPANSION,ACCESSIBILITY UPGRADES, AND ENERGY EFFICIENCY.
Location:
  • City of Taunton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2026/2027
    Project Manager: Edmond Libsch
    Estimated Total Contract Cost: $35,650,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: 100% Package Received (as of 04/06/2018 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/26/2013
    Project Initiation Form PIF Received 03/19/2013
    Project Initiation Form PIF Entered 02/26/2013
    Project Initiation Form PRC Submitted 03/19/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Management
    100% Design 100% Package Received 04/06/2018
    100% Design 100% Package Comments to DE 04/01/2014
    25% Design 25% Package Received 09/10/2013