Project Description:
MILLBURY- SUPERSTRUCTURE REPLACEMENT, M-22-038, I-90 RAMPS @ INTERCHANGE 11
Item 58= 4 (Deck, Railing) Item 59= 5 (Girders) Item 60= 6 AASHTO = 80.0 Bridge clearance = 14' 5" and has documented collision damage. District requests that PBU's be considered.
Location:
  • Town of Millbury
  • Construction Begins: Autumn 2020
    Resident Engineer: Jonathan Viner
    Construction Bid Price: $9,113,324.00
    District: District 3

    Contracts (3) Progress
    # 112498 -- Construction Contract
    Superstructure Replacement and Related Work Br. No. M-22-038 (Steel) along a Section of Interstate 90 at Interchange 11 Completed
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77891 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/09/2020
    Contract Information
    Project Designer:
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2013
    Project Initiation Form PIF Entered 02/27/2013
    Project Initiation Form PRC Submitted 02/27/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/15/2020
    Project Management
    100% Design 100% Package Received 06/11/2020
    25% Design 25% Package Received 01/04/2019
    25% Design 25% Package Comments to DE 03/04/2019
    25% Design Design Public Hearing 05/09/2019
    75% Design 75% Package Received 08/20/2019
    75% Design 75% Package Received 06/11/2020
    Final Design PS&E Received 06/11/2020
    Final Design PS&E to FAPRO 08/10/2020