Project Description:
WESTMINSTER- DECK REPLACEMENT, W-28-023, ROUTE 2A/140 OVER ROUTE 2
The project will include replacing the existing bridge deck. The bridge deck has been patched over a majority of it's surface area. The superstructure and substructure are in good condition.
Location:
  • Town of Westminster
  • Resident Engineer: Ryan Davison
    Construction Bid Price: $2,672,775.00
    District: District 3

    Contracts (1) Progress
    # 86777 -- Construction Contract
    Bridge Deck Replacement (Steel) Br. No. W-28-023 Route 2A/140 (Hager Park Road) over Route 2 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/18/2015
    Contract Information
    Project Designer:
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2013
    Project Initiation Form PIF Entered 02/28/2013
    Project Initiation Form PRC Submitted 02/28/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 02/28/2015
    Project Management
    100% Design 100% Package Received 01/23/2015
    25% Design 25% Package Comments to DE 11/17/2014
    25% Design Design Public Hearing 12/09/2014
    Final Design PS&E Received 02/18/2015
    Final Design PS&E to Peer Reviewer 02/09/2015
    Final Design Peer Review Comments to DE 02/20/2015
    Final Design PS&E to FAPRO 02/25/2015