Project Description:
CHELMSFORD- BRIDGE DECK REPLACEMENT, C-08-037, INCLUDING INTERSECTION IMPROVEMENTS AT ROUTE 4 & I-495 (EXIT 33)
Work consists of replacing the deck on C-08-037 along with a new signal to be installed at the intersection of Route 495 (Exit 32 NB) and Route 4.
Location:
  • Town of Chelmsford
  • Construction Begins: Spring 2018
    Resident Engineer: Vincent DeAngelo
    Construction Bid Price: $2,980,361.50
    District: District 4

    Contracts (2) Progress
    # 102196 -- Construction Contract
    Bridge Deck Replacement Br. No. C-08-037 and Intersection Improvements at Route 4 & I-495 (Exit 33). Completed
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/19/2018
    Contract Information
    Project Designer:
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2013
    Project Initiation Form PIF Entered 03/01/2013
    Project Initiation Form PRC Submitted 03/06/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 07/28/2017
    100% Design 100% Package Comments to DE 08/24/2017
    25% Design 25% Package Received 06/19/2015
    25% Design 25% Package Comments to DE 10/22/2015
    25% Design Design Public Hearing 01/25/2017
    75% Design 75% Package Received 04/13/2017
    Final Design PS&E Received 08/28/2017
    Final Design PS&E to FAPRO 08/28/2017