Project Description:
HOPEDALE- MILFORD- RESURFACING & INTERSECTION IMPROVEMENTS ON ROUTE 16 (MAIN STREET), FROM WATER STREET WEST TO APPROXIMATELY 120 FEET WEST OF THE MILFORD/HOPEDALE T.L AND THE INTERSECTION OF ROUTE 140.
The project involves resurfacing along Route 16, from Water Street to just west of the Hopedale Town line, a distance of 0.6 miles. Additional work includes sidewalk reconstruction, culvert repairs and related work. The project includes improvements to the intersection of Route 16 and Route 140, including upgraded signal equipment and widening where feasible.
Location:
  • Town of Hopedale
  • Town of Milford
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Jean-Pierre Telemaque
    Construction Bid Price: $2,495,203.00
    District: District 3

    Contracts (1) Progress
    # 109298 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 16 (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/14/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2013
    Project Initiation Form PIF Entered 03/05/2013
    Project Initiation Form PRC Submitted 03/18/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/10/2019
    Project Management
    100% Design 100% Package Received 05/08/2018
    100% Design 100% Package Comments to DE 09/14/2018
    25% Design 25% Package Received 02/24/2015
    25% Design 25% Package Comments to DE 07/24/2015
    25% Design Design Public Hearing 06/20/2017
    75% Design 75% Package Received 10/31/2017
    Final Design PS&E Received 12/07/2018
    Final Design PS&E Received - Resub 1 03/18/2019