Project Description:
NORTH ADAMS- INTERSECTION IMPROVEMENTS AT ROUTE 2 & PHELPS AVENUE
This project will address geometric and/or operational deficiencies at this 3-leg signalized intersection. The project will also upgrade pedestrian crossings, sidewalks and ramps to ADA compliance, and will upgrade the existing traffic signal to current standards.
Location:
  • City of North Adams
  • Construction Begins: Winter 2018/2019
    Resident Engineer: John Tietgens
    Construction Bid Price: $1,437,286.60
    District: District 1

    Contracts (1) Progress
    # 105568 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals and Bus Shelter Relocation) at Route 2 (Mohawk Trail) and Phelps Avenue Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/28/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2013
    Project Initiation Form PIF Entered 03/05/2013
    Project Initiation Form PRC Submitted 03/14/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/18/2018
    Project Management
    100% Design 100% Package Received 06/05/2018
    25% Design 25% Package Received 08/25/2014
    25% Design 25% Package Received 04/03/2015
    25% Design 25% Package Comments to DE 08/06/2015
    25% Design Design Public Hearing 03/08/2016
    75% Design 75% Package Received 03/16/2018
    75% Design 75% Package Comments to DE 04/24/2018
    Final Design PS&E Received 07/24/2018
    Final Design PS&E to FAPRO 08/06/2018