Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WESTMINSTER- REHABILITATION & BOX WIDENING ON ROUTE 140, FROM PATRICIA ROAD TO THE PRINCETON T.L.
The project involves roadway rehabilitation and minor widening on Route 140 from south of Patricia Road to the PrincetonTown line, a distance of 1.5 miles. Additional work involves minor geometric changes to vertical and horizontal alignment for improved sight distance. Drainage improvements include repairs to existing culverts that are in poor condition, as well as upgrades to guardrail and signs.
Location:
  • Town of Westminster
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2023
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $9,505,190.94
    Estimated Total Federal Participating Construction Cost: $10,108,853.47
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received - Resub 4 (as of 04/13/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTMINSTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,100,164.00
    State Cost: $1,275,041.00
    Total Cost: $6,375,205.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2013
    Project Initiation Form PIF Entered 03/06/2013
    Project Initiation Form PRC Submitted 03/18/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Management
    100% Design 100% Package Received 06/09/2022
    100% Design 100% Package Comments to DE 07/15/2022
    25% Design 25% Package Received 06/17/2019
    25% Design 25% Package Comments to DE 10/03/2019
    25% Design Design Public Hearing 02/05/2020
    75% Design 75% Package Received 05/19/2020
    Final Design PS&E Received 09/19/2022
    Final Design PS&E Received - Resub 1 10/07/2022
    Final Design PS&E Received - Resub 2 03/03/2023
    Final Design PS&E Received - Resub 3 03/24/2023
    Final Design PS&E Received - Resub 4 04/13/2023