Project Description:
WESTBOROUGH- SUPERSTRUCTURE REPLACEMENT (PEDESTRIAN BRIDGE), W-24-010, FISHER STREET OVER CSX
The existing steel thru truss/wood deck structure was built in 1915, repaired in 1941, and was closed in 1987. The bridge is currently used by pedestrians only. Deck = 3, Superstructure = 5, Substructure =5. The intent is to replace the existing superstructure with a new pedestrian bridge while re-using the existing granite block abutments.
Location:
  • Town of Westborough
  • Construction Begins: Summer 2021
    Resident Engineer: Peter Kurt
    Construction Bid Price: $1,795,750.00
    District: District 3

    Contracts (2) Progress
    # 114940 -- Construction Contract
    Pedestrian Bridge Superstructure Replacement Br. No. W-24-010 (Steel) Fisher Street over the CSX/MBTA Railroad Completed
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/15/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2013
    Project Initiation Form PIF Entered 03/07/2013
    Project Initiation Form PRC Submitted 03/07/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 06/26/2021
    Project Management
    25% Design 25% Package Received 09/11/2020
    25% Design 25% Package Comments to DE 10/16/2020
    25% Design Design Public Hearing 02/18/2021
    75% Design 75% Package Received 03/26/2021
    Final Design PS&E Received 05/21/2021
    Final Design PS&E to FAPRO 06/14/2021