Project Description: |
BARNSTABLE- INTERSECTION IMPROVEMENTS @ FALMOUTH ROAD (ROUTE 28) & OSTERVILLE-WEST BARNSTABLE ROAD
This project proposes to address vehicular safety by upgrading traffic signals to include exclusive left turn lanes at the Route 28 approaches in addition to emergency vehicle pre-emption. There is also a need to improve bicycle and pedestrian accommodation at the intersection in addition to updating pavement markings and signage.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Kimberley Sloan![]() |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|