Project Description: |
BARNSTABLE- INTERSECTION IMPROVEMENTS @ FALMOUTH ROAD (ROUTE 28) & OSTERVILLE-WEST BARNSTABLE ROAD
This project proposes to address vehicular safety by upgrading traffic signals to include exclusive left turn lanes at the Route 28 approaches in addition to emergency vehicle pre-emption. There is also a need to improve bicycle and pedestrian accommodation at the intersection in addition to updating pavement markings and signage.
|
Location: |
|
Construction Begins: | Spring 2019 |
Resident Engineer: | Michael King |
Construction Bid Price: | $3,366,212.80 |
District: | District 5 |
|
Bridges |
|
|
|
|