Project Description:
BARNSTABLE- INTERSECTION IMPROVEMENTS @ FALMOUTH ROAD (ROUTE 28) & OSTERVILLE-WEST BARNSTABLE ROAD
This project proposes to address vehicular safety by upgrading traffic signals to include exclusive left turn lanes at the Route 28 approaches in addition to emergency vehicle pre-emption. There is also a need to improve bicycle and pedestrian accommodation at the intersection in addition to updating pavement markings and signage.
Location:
  • Town of Barnstable
  • Construction Begins: Spring 2019
    Resident Engineer: Michael King
    Construction Bid Price: $3,366,212.80
    District: District 5

    Contracts (2) Progress
    # 105915 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Falmouth (Route 28) and Osterville - West Barnstable Roads Completed
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/29/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2013
    Project Initiation Form PIF Entered 03/07/2013
    Project Initiation Form PRC Submitted 03/07/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 11/17/2017
    100% Design 100% Package Comments to DE 01/08/2018
    25% Design 25% Package Received 09/08/2014
    25% Design 25% Package Received 11/19/2015
    25% Design 25% Package Comments to DE 06/04/2015
    25% Design 25% Package Comments to DE 01/22/2016
    25% Design Design Public Hearing 10/27/2016
    75% Design 75% Package Received 05/05/2017
    75% Design 75% Package Comments to DE 08/09/2017
    Final Design PS&E Received 03/01/2018
    Final Design PS&E to Peer Reviewer 04/20/2018
    Final Design Peer Review Comments to DE 04/25/2018
    Final Design PS&E to FAPRO 08/31/2018