| Project Description: |
HUBBARDSTON- RESURFACING AND RELATED WORK ON BURNSHIRT ROAD
The project involves resurfacing Burnshirt Road, from the Barre Town line to the Templeton Town line, a distance of 1.75 miles. Related work includes upgrades to guardrail, tree trimming, adjusting of drainage structures and pavement markings.
|
| Location: |
|
| Resident Engineer: | Ryan Davison![]() |
| Construction Contract Value: | $1,103,640.00 |
| Construction Bid Price: | $958,383.25 |
| Initial Construction Estimate: | $1,081,008.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||