Project Description:
HUBBARDSTON- RESURFACING AND RELATED WORK ON BURNSHIRT ROAD
The project involves resurfacing Burnshirt Road, from the Barre Town line to the Templeton Town line, a distance of 1.75 miles. Related work includes upgrades to guardrail, tree trimming, adjusting of drainage structures and pavement markings.
Location:
  • Town of Hubbardston
  • Resident Engineer: Ryan Davison
    Construction Contract Value: $1,103,640.00
    Construction Bid Price: $958,383.25
    Initial Construction Estimate: $1,081,008.00
    District: District 3

    Contracts (1) Progress
    # 83130 -- Construction Contract
    Resurfacing and Related Work on a Section of Burnshirt Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/24/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2013
    Project Initiation Form PIF Entered 03/08/2013
    Project Initiation Form PRC Submitted 03/18/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 06/28/2014
    Project Management
    100% Design 100% Package Received 06/20/2014
    25% Design 25% Package Received 06/06/2014
    75% Design 75% Package Received 06/06/2014
    Final Design PS&E Received 06/20/2014
    Final Design PS&E to FAPRO 06/25/2014