Project Description:
BOSTON- CONSTRUCTION OF A MAINTENANCE FACILITY FOR THE GREENWAY CONSERVANCY
This project is to provide a Maintenance Facility for the the storage of Greenway maintenance equipment, materials, plants and maintenance personnel. 7000 sf facility to be constructed on Parcel 27A including a designated outdoor space for composting and storage.
Location:
  • City of Boston
  • Construction Begins: Summer 2022
    Resident Engineer: Ahmad Ilyas
    Construction Bid Price: $9,627,880.00
    District: District 6

    Contracts (1) Progress
    # 117280 -- Construction Contract
    Construction of a Maintenance Facility for the Rose Fitzgerald Kennedy Greenway Conservancy, C/AT parcel 27A, at the Intersection of I-93 and I-90 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/23/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Received 03/08/2013
    Project Need Form PNF Entered 03/08/2013
    Project Need Form PNF Approved 03/08/2013
    Project Initiation Form PIF Received 03/01/2013
    Project Initiation Form PIF Entered 03/08/2013
    Project Initiation Form PRC Submitted 03/08/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 01/29/2022
    Project Management
    100% Design 100% Package Received 09/11/2020
    25% Design 25% Package Received 03/18/2020
    25% Design 25% Plans Complete 03/18/2020
    75% Design 75% Package Received 06/19/2020
    75% Design 75% Package Comments to DE 07/17/2020
    Final Design PS&E Received 01/24/2022
    Final Design PS&E to FAPRO 01/24/2022