Project Description:
EASTON- INTERSECTION IMPROVEMENTS AT WASHINGTON STREET (ROUTE 138) AND UNION STREET
The project is intended to improve safety at the intersection through the installation of an actuated traffic signal, minor widening of the Union Street approach to two lanes, and construction of a left turn lane on Route 138 SB; provide sidewalk extensions in the vicinity of the intersection and restriping of shoulders to better accommodate bicycles.
Location:
  • Town of Easton
  • Construction Begins: Spring 2019
    Resident Engineer: Eric Borman
    Construction Bid Price: $1,685,464.00
    District: District 5

    Contracts (2) Progress
    # 105771 -- Construction Contract
    Intersection Improvements and Related Work at Washington (Route 138) and Union Streets Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/21/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/11/2013
    Project Initiation Form PIF Entered 07/09/2013
    Project Initiation Form PRC Submitted 07/09/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 09/14/2017
    100% Design 100% Package Comments to DE 11/20/2017
    25% Design 25% Package Received 07/28/2014
    25% Design 25% Package Comments to DE 06/17/2015
    25% Design 25% Package Approved 06/03/2016
    25% Design Design Public Hearing 07/14/2016
    75% Design 75% Package Received 02/06/2017
    75% Design 75% Package Comments to DE 05/08/2017
    Final Design PS&E Received 01/11/2018
    Final Design PS&E Received - Resub 1 04/27/2018
    Final Design PS&E Received - Resub 2 07/10/2018