MANCHESTER BY THE SEA- SAFE ROUTES TO SCHOOL (MEMORIAL ELEMENTARY)
The project includes reconstruction of the sidewalk on the north side of Summer Street from the school exit driveway past its intersection with Lincoln Street to just east of the gas station driveway. The school exit driveway will be reconstructed to include a 10’ wide asphalt sidewalk with 3’ grass buffer and granite curbing along the westerly boundary of the driveway from Summer Street to the school’s entrance. A raised crosswalk at the school’s entrance, new sidewalk along the northerly edge of the school parking lot and new sidewalk along the easterly side of Lincoln Street will allow pedestrians to access the school from Summer Street. The improvements will include installation of wheelchair ramps, installation of signs and pavement markings, minor drainage modifications, pavement overlay and new bicycle racks.
Location:
  • Town of Manchester By the sea
  • Resident Engineer: Carmen Ilardi
    Construction Contract Value: $591,864.00
    Construction Bid Price: $518,917.30
    Initial Construction Estimate: $495,791.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 83945 -- Construction Contract
    Sidewalk Reconstruction and Related Work (Including Flashing Beacon) on Sections of Route 127 (Summer Street), Lincoln Street and School Driveway (Safe Routes to School - Memo Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/29/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/13/2013
    Project Initiation Form PIF Entered 03/13/2013
    Project Initiation Form PRC Submitted 03/13/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/02/2014
    Project Management
    100% Design 100% Package Received 01/07/2014
    25% Design 25% Package Received 05/30/2013
    25% Design 25% Package Comments to DE 10/16/2013
    25% Design Design Public Hearing 11/21/2013
    75% Design 75% Package Received 05/30/2013
    75% Design 75% Package Comments to DE 10/16/2013
    Final Design PS&E Received 04/03/2014