NORTHBOROUGH- SHREWSBURY- RECONSTRUCTION ON ROUTE 9 & ROUTE 20 RAMP IMPROVEMENTS
The proposed project involves widening of the Route 9 westbound barrel to provide a longer acceleration lane. Additional improvements include minor horizontal geometric improvements at the interwsection of the Route 9 westbound off ramp and Route 20.
Location:
  • Town of Northborough
  • Town of Shrewsbury
  • Construction Begins: Summer 2017
    Resident Engineer: Roger Wykes
    Construction Bid Price: $1,627,299.85
    District: District 3

    Contracts (1) Progress
    # 100200 -- Construction Contract
    Roadway and Ramp Reconstruction and Related Work at the Intersection of Routes 9 and 20 (Boston and Hartford Turnpikes) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/04/2017
    Contract Information
    Project Designer:
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2013
    Project Initiation Form PIF Entered 03/15/2013
    Project Initiation Form PRC Submitted 03/18/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 04/15/2017
    Project Management
    100% Design 100% Package Received 02/16/2017
    25% Design 25% Package Received 03/11/2015
    25% Design 25% Package Comments to DE 07/13/2015
    25% Design Design Public Hearing 11/04/2015
    75% Design 75% Package Received 05/02/2016
    75% Design 75% Package Comments to DE 06/10/2016
    Final Design PS&E Received 02/16/2017
    Final Design PS&E to FAPRO 04/03/2017