Project Description: |
WEST SPRINGFIELD- BRIDGE REHABILITATION, BRIDGE W-21- 27, ROUTE 20 (PARK AVENUE) OVER ROUTE 5
The scope of the project includes a feasibility study of possible rehabilitation options for Bridge No. W-21-027, AKA Route 5 Tunnel, carrying Route 20 (Park Ave.) over Route 5. The existing structure was built in 1952.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Alwin Ramirez![]() |
Estimated Total Contract Cost: | $3,453,400.00 |
Estimated Total Federal Participating Construction Cost: | $3,719,240.00 |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|