Project Description:
WESTMINSTER- INTERSECTION IMPROVEMENTS, ROUTE 2A AT ROUTE 140
The proposed project involves intersection improvements at Route 2A at Route 140, including replacing the traffic signals and full-depth pavement reconstruction including minor widening and geometric improvements.
Location:
  • Town of Westminster
  • Construction Begins: Spring 2019
    Resident Engineer: Byron Beauregard
    Construction Bid Price: $1,896,054.65
    District: District 3

    Contracts (2) Progress
    # 106507 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Hager Park/State Roads (Route 140/2A) and East Main Street/Ramps (Route 2A/2) Completed
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/15/2013
    Project Initiation Form PIF Entered 03/15/2013
    Project Initiation Form PRC Submitted 03/18/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 12/01/2018
    Project Management
    100% Design 100% Package Received 03/15/2018
    100% Design 100% Package Comments to DE 05/31/2018
    25% Design 25% Package Received 05/31/2016
    25% Design 25% Package Comments to DE 10/17/2016
    25% Design Design Public Hearing 06/06/2017
    75% Design 75% Package Received 10/23/2017
    75% Design 75% Package Comments to DE 12/26/2017
    Final Design PS&E Received 09/12/2018
    Final Design PS&E to Peer Reviewer 06/04/2018
    Final Design Peer Review Comments to DE 06/27/2018
    Final Design PS&E Received - Resub 1 11/06/2018