Project Description:
WESTWOOD- SAFE ROUTES TO SCHOOL (DOWNEY SCHOOL)
Project consists of constructing an asphalt sidewalk on the west side of Downey Street and constructing ADA complian wheelchair ramps, applying crosswalk and stop bar striping and installing MUTCD compliant regulatory and warning signage. In addition sidewalks along the west side of Forbes Road and the construction of new asphalt sidwalks where needed. A new crosswalk and associated signage will be installed at the intersection of Forbes Road and Glandore Road.
Location:
  • Town of Westwood
  • Resident Engineer: Carmen Ciampi
    Construction Contract Value: $493,598.00
    Construction Bid Price: $441,180.00
    Initial Construction Estimate: $481,050.00
    District: District 6

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84589 -- Construction Contract
    Sidewalk Reconstruction and Related Work (Including Flashing Beacon) on Sections of Downy Street and Forbes Road (Safe Routes to School Downey Elementary School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2013
    Project Initiation Form PIF Entered 03/18/2013
    Project Initiation Form PRC Submitted 03/18/2013
    Project Review Committee PRC Approved 03/21/2013
    Project Status Advertised 08/30/2014
    Project Management
    100% Design 100% Package Received 03/25/2014
    100% Design 100% Package Comments to DE 05/23/2014
    25% Design 25% Package Received 09/03/2013
    25% Design 25% Package Comments to DE 11/15/2013
    25% Design Design Public Hearing 02/26/2014
    75% Design 75% Package Received 09/03/2013
    75% Design 75% Package Comments to DE 11/15/2013
    Final Design PS&E Received 08/18/2014
    Final Design PS&E to FAPRO 08/27/2014