Project Description:
SANDISFIELD- BRIDGE MAINTENANCE, S-03-033, ROUTE 8 (SOUTH MAIN STREET) OVER WEST BRANCH FARMINGTON RIVER (PHASE I)
This bridge is located approximately 2.5 miles north of the CT state line. This proposed maintenance contract includes stripping and replacing the wearing surface; repairing deteriorated deck section(s) as required; and applying epoxy bonding. It is estimated that approximately 3% of the of the deck will require full depth excavation, and another 25% may require partial depth excavation. Proposed work also includes installation of new steel bars, in kind, where reinforcing steel exhibits section loss; application of deck membrane; and approach slab repairs, excluding recently repaired joints. Spalling will be repaired in the backwalls, piers, and concrete railing. Two-stage construction is anticipated; with traffic management to consist of alternating one-way traffic with a temporary solar signal.
Location:
  • Town of Sandisfield
  • Resident Engineer: Joseph Mastroianni
    Construction Contract Value: $703,843.18
    Construction Bid Price: $628,926.00
    Initial Construction Estimate: $676,626.70
    District: District 1

    Contracts (1) Progress
    # 81428 -- Construction Contract
    Bridge Deck Repairs (S-03-033) (Concrete) South Main Street (Route 8) over the West Branch Farmington River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/29/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/26/2013
    Project Initiation Form PIF Entered 03/26/2013
    Project Initiation Form PRC Submitted 03/26/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 03/15/2014
    Project Management
    100% Design 100% Package Received 11/19/2013
    Final Design PS&E Received 12/31/2013
    Final Design PS&E to FAPRO 02/10/2014