BURLINGTON- TYNGSBOROUGH- PAVEMENT PRESERVATION AT VARIOUS LOCATIONS ON ROUTE 3
This project will resurface Route 3 North in Burlington to Tyngsborough (MA/NH State Line) (SHRP2) from Mile post 72.0 to 91.5 a project length of 19.5 miles.
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Burlington
  • Town of Chelmsford
  • City of Lowell
  • Town of Tyngsborough
  • Town of Westford
  • Resident Engineer: Amir Pakyari
    Construction Contract Value: $9,358,798.00
    Construction Bid Price: $8,147,999.00
    Initial Construction Estimate: $7,708,416.00
    District: District 4

    Contracts (1) Progress
    # 81581 -- Construction Contract
    Pavement Preservation and Related Work along a Section of Route 3. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/18/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2013
    Project Initiation Form PIF Entered 05/14/2013
    Project Initiation Form PRC Submitted 05/14/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 03/29/2014
    Project Management
    100% Design 100% Package Received 11/04/2013
    100% Design 100% Package Received 12/19/2013
    100% Design 100% Package Received 01/06/2014
    100% Design 100% Package Comments to DE 11/18/2013
    25% Design 25% Package Received 08/28/2013
    25% Design 25% Package Approved 09/04/2013
    75% Design 75% Package Received 08/28/2013
    75% Design 75% Package Comments to DE 09/04/2013
    Final Design PS&E Received 01/06/2014
    Final Design PS&E Received 01/24/2014
    Final Design PS&E Received 03/29/2014
    Final Design PS&E Received 05/06/2014
    Final Design PS&E to FAPRO 12/23/2013
    Final Design PS&E to FAPRO 05/08/2014