Project Description:
WINCHENDON- RESURFACING & RELATED WORK ON ROUTE 12, FROM MILL STREET/BEGINNING OF STATE HIGHWAY TO NEW HAMPSHIRE STATE LINE (2.5 MILES)
The project will resurface Route 12 in Winchedon from Milepoint 61.9 to 64.4 for a project length of 2.5 miles.
Location:
  • Town of Winchendon
  • Construction Begins: Autumn 2017
    Resident Engineer: Victor LaMountain
    Construction Bid Price: $1,143,888.30
    District: District 2

    Contracts (2) Progress
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final
    # 99870 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 12 (School Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/27/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2013
    Project Initiation Form PIF Entered 05/14/2013
    Project Initiation Form PRC Submitted 05/14/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 03/04/2017
    Project Management
    100% Design 100% Package Received 01/23/2017
    100% Design 100% Package Comments to DE 02/03/2017
    25% Design 25% Package Received 10/18/2016
    25% Design 25% Package Comments to DE 11/17/2016
    75% Design 75% Package Received 10/18/2016
    75% Design 75% Package Comments to DE 11/17/2016
    Final Design PS&E Received 01/23/2017
    Final Design PS&E Received - Resub 1 02/14/2017